WELLFLEET — When tenants get the keys to their new apartments at Wellfleet’s Lawrence Hill affordable housing complex next year, their drains may lead to holding tanks rather than the cluster wastewater system the town is in charge of building.

The cluster system, which will also serve the town’s police and fire stations, elementary school, and a few nearby homes, is being built by the Robert B. Our Company, but it’s not clear exactly when it is expected to be finished.
The construction contract and Notice to Proceed for the project were signed by town officials and company representatives on May 16. The town’s bid documents had specified that there be at most 355 days between the Notice to Proceed date and the end of construction — but the construction contract itself allows for 450 days.
“Substantial completion” must be achieved by early August 2026 and “final close-out” by late September 2026, according to copies of the contract and Notice to Proceed provided by town officials to the Independent.
The developer’s timeline on the town’s housing website, wellfleethousing.org, says that the lottery for the 46 apartments at Lawrence Hill is supposed to take place this fall, with lease-up in January 2026 and move-in shortly after that.
Assistant Town Administrator John Bugbee told the Independent that delaying the move-in past early 2026 is a “possibility” and “something that we have discussed,” and that town officials would have a better sense of the timing by the fall.
Wellfleet Town Administrator Tom Guerino told the Independent that the town has an “understanding” with the Our Company that the cluster system will be finished by January or February 2026, but he wouldn’t say whether that agreement was verbal or in writing.
“No, I’m not going on the record with that,” Guerino said.
Bugbee said that the town had to offer a longer construction schedule in order to attract bidders.
“We couldn’t go out to bid — and get a contractor to bid — unless we gave them time to do the project in the standard amount of time,” Bugbee said. “But they also know that that’s a little longer than what [affordable housing developer] POAH is looking for in terms of occupancy, and they’ve agreed to work with us on that.”
Preservation of Affordable Housing (POAH) is a national nonprofit developer; it has partnered with the Community Development Partnership, a nonprofit that serves the Outer and Lower Cape, on the Lawrence Hill project.
Bugbee also said there is no construction schedule for the cluster waste treatment system.
“The housing units are already being constructed, and this [wastewater] project has its own engineers and construction company,” he said. “So that’s a lot of people who have to come together on how all of this is going to work.
“That’s why we don’t have the schedule set in stone,” Bugbee said. “Instead, we just say, ‘Get it done by X date.’
“If it looks like it won’t line up, then we’ll look at a contingency plan,” Bugbee continued. “One option we’re considering is pumping the wastewater into holding tanks, and then the tanks would be pumped until the treatment plant is up and running.”
Jay Coburn, CEO of the Community Development Partnership, said he had been told there would be a backup plan so that tenants can move in on schedule.
“There will be an interim way to collect and dispose of the wastewater,” Coburn said. “The town has stated that if they’re not able to get that system completed in time, that there will be contingencies so that there is not a delay in the occupancy.”
The town began planning work on the Lawrence Hill project about five years ago, Coburn told the Independent in April, and the $4.6-million cluster wastewater system was authorized by town meeting votes in 2021 and 2023. The town secured a $3-million state grant for the project in the fall of 2023, which reduced the amount that taxpayers will have to pay.
The 46 apartments will be the first affordable rental units to open in Wellfleet since 2017, when Community Housing Resource finished a six-unit project on Gull Pond Road.
“The only positive moves we’ve made on managing our wastewater problem — our nitrogen problem — is through affordable housing,” said Sharon Rule-Agger, chair of the Wellfleet Local Housing Partnership. “Housing is complicated, and wastewater management is complicated. They cannot be done in silos.”
According to the town’s Targeted Watershed Management Plan, the cluster system will reduce the town’s nitrogen emissions into its waterways by 263 kilograms per year compared to current levels.
Abby Rose, a construction manager for the Our Company, said there was a “kickoff meeting” last week between town officials, the company, and engineering consultant David Formato of Fuss & O’Neill.
The company plans to break ground on the cluster system in early July, Rose said.